This Sat. we will be taking a tour of the new bridge site on the upper Walian. We may do some work. Not much though.
Meet at Grace at 9:00 ride 9:30 .
Meet at Grace at 9:00 ride 9:30 .
- westcoastjack
- Posts: 43
- Joined: Sat Dec 28, 2013 2:34 am
Re: Walian bridge project
Hi Greg..
I cannot make it...this time, Sorry. I am watching though. Notifications are working. So far the 5th is clear for me. The 12th I am away.
Jack
Well..My other stuff is cancelled so I am tentative for this Saturday. Otherwise the 5th.
I cannot make it...this time, Sorry. I am watching though. Notifications are working. So far the 5th is clear for me. The 12th I am away.
Jack
Well..My other stuff is cancelled so I am tentative for this Saturday. Otherwise the 5th.
get dirty,clean,repeat
Re: Walian bridge project
Sadly I won't be able to make it tomorrow either, when's the next outing planned for?
Re: Walian bridge project
We will probably be going out next Sat. I will post sometime in the middle of next week.
- dodgeboykim
- Posts: 32
- Joined: Thu Feb 26, 2015 5:59 am
Re: Walian bridge project
And Ken said no one ever reads these posts.
Re: Walian bridge project
I have been watching
Re: Walian bridge project
Count your lucky stars you weren't there! We hit a regular monsoon on the way home and "some people' forgot to pack rain pants = sticky buns...... .
Good news is the footbridge is fine and all well.
Good news is the footbridge is fine and all well.
Re: Walian bridge project
From Ken...
Update on the bridge build.;
We are tentatively scheduling the delivery ( Dave G. ) and assembly of the upper Walian Bridge (B3) for Saturday the 26th of November.
- I have contacted the guy (Barry) who expertly placed the last bridge and he has agreed to come up on the following weekend to fix up the approach and place the bridge for us. ( Saturday the 3rd Dec.)
-The parts are all cut and fabrication/welding/painting will happen next week.
-there's still some work to be done if we can't get a bobcat up there to temporarily fill 10 cross ditches so Dave's truck won't bottom out. We'll have to drag logs down to fill them up a bit.
- I'll also be posting a list of hardware we'll need..nuts/bolts/nails etc if anyone would like to donate to the cause. (Hopefully tomorrow)
-Getting the deck on should go pretty quick as it's only 40 feet and the material is already on site. (sat or Sunday)
Stay tuned!
Update on the bridge build.;
We are tentatively scheduling the delivery ( Dave G. ) and assembly of the upper Walian Bridge (B3) for Saturday the 26th of November.
- I have contacted the guy (Barry) who expertly placed the last bridge and he has agreed to come up on the following weekend to fix up the approach and place the bridge for us. ( Saturday the 3rd Dec.)
-The parts are all cut and fabrication/welding/painting will happen next week.
-there's still some work to be done if we can't get a bobcat up there to temporarily fill 10 cross ditches so Dave's truck won't bottom out. We'll have to drag logs down to fill them up a bit.
- I'll also be posting a list of hardware we'll need..nuts/bolts/nails etc if anyone would like to donate to the cause. (Hopefully tomorrow)
-Getting the deck on should go pretty quick as it's only 40 feet and the material is already on site. (sat or Sunday)
Stay tuned!
Re: Walian bridge project
So nice when a plan comes together